Overview
In 2013-14, the Directorate again delivered a significant capital works program, totalling $64.3 million, following on from the $90.2 million program in 2012-13 and $92.3 million program delivered in 2011-12.
Highlights for the year were the opening of the final stages of Neville Bonner Primary School and Franklin Early Childhood School, the reopening of Taylor Primary School and the expansion of Macgregor, Majura and Duffy Primary Schools.
All major projects were either completed or were on target to be delivered by the scheduled completion date.
New Schools and Childcare Centres
Primary School in Coombs
Redesign work for a smaller school to reflect revised demographic projections was completed to Final Sketch Plan stage in the 2012-13 reporting period. The procurement process to engage a builder for the project was commenced with an expected appointment early in the 2014-15 reporting period.
The Government is investing a total of $47.25 million in the construction of the primary school in Coombs, the first school in the district of Molonglo. The new school is scheduled to open at the start of the 2016 school year.
Holder Early Childhood Centre
Construction of the Holder Early Childhood Centre was completed during the reporting period. This facility was the first purpose-built early childhood centre in the ACT under the National Quality Framework for Early Childhood Education and Care. The new centre provides 124 places supporting families in the Weston Creek area and the new development areas in the Molonglo district.
School Improvements
Taylor Primary School Rectification
Rectification and upgrade works were completed at Taylor Primary School ready for the start of the 2014 school year. This included the removal and replacement of the external asbestos wall sheeting. The works also included the expansion of the on-site childcare centre from 26 to 65 places.
Canberra College Cares Program
Designs for the new Canberra College Cares (CCCares) facility on the Woden campus of Canberra College were completed and construction commenced during the reporting period. The new facility will enable students and their children attending the CCCares program to transfer from the college's Weston campus and to be integrated into the college's Woden campus.
This project is scheduled to be completed ready for the start of the 2015 school year.
Sustainable Learning Trade Training Centre - Tuggeranong Network
The Australian Government approved a grant in December 2011 to establish the Tuggeranong Sustainable Learning Trade Training Centre. This project involves work at four high schools (Calwell and Lanyon High schools and Caroline Chisholm and Wanniassa schools) and two colleges (Erindale and Lake Tuggeranong) across the Tuggeranong School Network.
The hospitality services extension and cafe at Erindale College and the construction services workshop at Lake Tuggeranong College were completed during the reporting period. A project manager was appointed to manage refurbishment works at Lake Tuggeranong College and four high schools. Works were completed at the four high schools with the Lake Tuggeranong College metal and automotive workshop refurbishment to be completed early in the 2014-15 reporting period.
Trade Skills Centre - Belconnen Network
The Australian Government approved a grant in January 2013 to establish the Belconnen Trade Skills Centre in the Belconnen School Network. The project will involve facility improvements at Hawker College and University of Canberra Senior Secondary College Lake Ginninderra, University of Canberra High School Kaleen, Canberra and Belconnen High schools, Melba Copland Secondary School and Kingsford Smith School. Detailed design work commenced during the reporting period.
Duffy Primary School Extension
New modular classrooms were manufactured off-site and assembled on-site at the school during the reporting period. This extended Duffy Primary School to a full three-stream school (three classes in each year group from kindergarten to year 6). Works were completed ready for the start of the 2014 school year.
Majura Primary School Extension
Construction work to extend Majura Primary School was completed ready for the start of the 2014 school year. This extended Majura Primary School to a full four-stream school (four classes in each year group from kindergarten to year 6).
Macgregor Primary School Extension
Construction work to extend Macgregor Primary School was completed ready for the start of the 2014 school year. This extended Macgregor Primary School to a full four-stream school (four classes in each year group from kindergarten to year 6).
Preschool Expansions
Construction of the new Deakin preschool was completed during the reporting period.
Designs for upgrades and expansion of the Latham and Campbell preschools were completed with construction commenced during the reporting period.
Upgrade and expansion works were completed at Watson preschool and refurbishment works were completed at Pearce and Turner preschools during the reporting period.
Childcare Centres
Upgrade and expansion works were completed at Campbell Cottage, Greenway Childcare Centre, Narrabundah Cottage and Nimbin Childcare Centre in Narrabundah.
Designs were completed to upgrade and expand the Gungahlin centre, Treehouse in the Park centre in Turner and Appletree House centre in Wanniassa during the reporting period.
Construction work commenced on the Fyshwick, Forrest, Treehouse in the Park and Appletree House centres during the reporting period. Work will commence on the Gungahlin centre early in the 2014-15 reporting period.
Design work commenced during the reporting period to upgrade and expand the Totom House centre in Kaleen.
A feasibility study to review the Civic Early Childhood Centre was completed during the 2013-14 reporting period.
Belconnen High School Modernisation - Stage 1
Planning and consultation work was undertaken during the reporting period, with work progressed on the master plan and infrastructure plans. Construction and demolition works will be undertaken during the 2014-15 financial year.
Tuggeranong Introductory English Centre
Designs for a new centre at Wanniassa Hills Primary School were completed during the reporting period. Construction will be undertaken during the 2014-15 financial year.
School Infrastructure for the Future
Projects completed under this program during the reporting period included the construction of a library and the refurbishment of classrooms at Malkara School, staffroom refurbishment and toilet upgrades at Forrest Primary School, landscape improvements including a learn to ride facility at Southern Cross Early Childhood School, a dirt bike track at Melrose High School, restoration of the grass oval at Hawker Primary School and the upgrade of information and communication technology infrastructure in schools.
Older Schools Upgrade Program
Major upgrade works were completed at Hughes and Yarralumla Primary Schools in the 2013-14 reporting period.
Security Fences
New security fences were installed during the reporting period at University of Canberra Senior Secondary College Lake Ginninderra, Wanniassa School (senior campus) and Fraser, Macgregor, Maribyrnong, Mount Rogers and Red Hill Primary Schools.
Designs for security fences at Arawang, Duffy and Mawson Primary schools were completed during the reporting period.
Car Parks and Traffic Improvements
Construction works at Weetangera and Curtin Primary schools and Southern Cross Early Childhood School were completed during the reporting period.
Designs were completed for car park upgrades and expansions at Majura and Macgregor Primary schools during the reporting period.
School Roof Replacement Program
A major roof replacement was completed at Chapman Primary School in the 2013-14 reporting period. Works were commenced at Canberra High School and will be completed during the next reporting period.
Digital Front Signage
New digital signs were installed at the front of Namadgi School and Neville Bonner Primary School during the reporting period.
Environmental Sustainability
A total of $1.2 million was allocated from the annual schools capital upgrades program to support the Directorate's strategic priorities for environmental sustainability initiatives. Refer to Section B4 for an overview of the projects and policies implemented during the 2013-14 reporting period.
Capital Works Schedules
The Directorate's capital works management program for 2013-14, detailing the completed projects and works still in progress at the year's end, is shown in Table F3.1.
Table F3.1: Capital works management 2013-14
New Capital Works
Project |
Original project value $'000 |
Revised project value $'000 |
Prior year exp. $'000 |
Actual finance 2013-2014 $'000 |
Actual exp. 2013-2014 $'000 |
Total exp. to date $'000 | Estimated completion date | Actual completion date | Project approval year |
---|---|---|---|---|---|---|---|---|---|
Canberra College Cares - new building at Woden Campus | 14,000 | 14,000 | 0 | 4,253 | 4,260 | 4,260 | Feb-15 | N/A | 2013-14 |
School Infrastructure for the Future | 3,345 | 3,345 | 0 | 2,089 | 2,799 | 2,799 | Jun-14 | N/A | 2013-14 |
Childcare centre upgrades - Stage 2 | 2,000 | 2,000 | 0 | 181 | 183 | 183 | Jun-15 | N/A | 2013-14 |
Belconnen High School modernisation - Stage 1 | 2,000 | 2,000 | 0 | 127 | 132 | 132 | Jun-15 | N/A | 2013-14 |
Tuggeranong Introductory English Centre | 1,800 | 1,800 | 0 | 226 | 228 | 228 | Jun-15 | N/A | 2013-14 |
Coombs P-6 school construction funding | 0 | 47,250 | 0 | 19 | 19 | 19 | Jan-16 | N/A | 2013-14 |
Capital Upgrades
Project |
Original project value $'000 |
Revised project value $'000 |
Prior year exp. $'000 |
Actual finance 2013-2014 $'000 |
Actual exp. 2013-2014 $'000 |
Total exp. to date $'000 | Estimated completion date | Actual completion date | Project approval year |
---|---|---|---|---|---|---|---|---|---|
Older school upgrades | 2,740 | 2,740 | 0 | 2,405 | 2,431 | 2,431 | Jun-14 | Jun-14 | 2013-14 |
Excellence and Enterprise – high school frontages | 0 | 0 | 0 | 534 | 171 | 171 | Jun-14 | Jun-14 | 2013-14 |
New school facilities | 960 | 960 | 0 | 580 | 945 | 945 | Jun-14 | Jun-14 | 2013-14 |
School infrastructure improvements | 4,670 | 4,412 | 0 | 4,463 | 4,469 | 4,469 | Jun-14 | Jun-14 | 2013-14 |
Building compliance upgrades | 1,060 | 1,060 | 0 | 1,002 | 1,105 | 1,105 | Jun-14 | Jun-14 | 2013-14 |
School security improvements | 1,220 | 1,220 | 0 | 1,237 | 1,206 | 1,206 | Jun-14 | Jun-14 | 2013-14 |
School safety improvements | 1,660 | 1,660 | 0 | 1,629 | 1,660 | 1,660 | Jun-14 | Jun-14 | 2013-14 |
Environmentally sustainable design initiatives | 1,220 | 1,220 | 0 | 1,186 | 1,190 | 1,190 | Jun-14 | Jun-14 | 2013-14 |
Childcare facilities | 425 | 425 | 0 | 212 | 212 | 212 | Jun-14 | N/A | 2013-14 |
Total new and upgrades works | 37,100 | 84,092 | 0 | 20,143 | 21,010 | 21,010 | - | - | - |
Work In Progress
Project |
Original project value $'000 |
Revised project value $'000 |
Prior year exp. $'000 |
Actual finance 2013-2014 $'000 |
Actual exp. 2013-2014 $'000 |
Total exp. to date $'000 | Estimated completion date | Actual completion date | Project approval year |
---|---|---|---|---|---|---|---|---|---|
Duffy Primary School expansion | 2,800 | 2,800 | 315 | 2,289 | 2,352 | 2,667 | Dec-13 | Jan-14 | 2012-13 |
Carbon Neutral Schools - Stage 1 | 3,500 | 3,500 | 176 | 601 | 807 | 983 | Jun-16 | N/A | 2012-13 |
Childcare centre improvements | 0 | 900 | 0 | 111 | 142 | 142 | Jun-14 | N/A | 2012-13 |
COAG Universal Access to Preschools - Stage 1 expansion works | 6,200 | 6,200 | 3,196 | 1,803 | 1,685 | 4,881 | Apr-14 | N/A | 2011-12 |
West Macgregor development - Macgregor Primary School expansion | 5,650 | 5,899 | 2,185 | 3,694 | 3,203 | 5,388 | Oct-13 | Sep-13 | 2011-12 |
Upgrade of early childhood facilities | 0 | 7,716 | 2,143 | 3,662 | 3,920 | 6,063 | Dec-13 | N/A | 2011-12 |
Holder Early Childhood Centre | 0 | 6,209 | 734 | 4,880 | 4,896 | 5,630 | May-14 | May-14 | 2011-12 |
Sustainable Learning Trade Training Centre - Tuggeranong | 10,207 | 8,301 | 451 | 5,580 | 5,691 | 6,142 | Apr-14 | N/A | 2011-12 |
Belconnen Trade Skills Centre | 8,968 | 8,120 | 0 | 66 | 66 | 66 | Jun-16 | N/A | 2013-14 |
North Watson development - Majura Primary School expansion | 4,400 | 4,680 | 1,512 | 2,809 | 2,574 | 4,086 | May-14 | Sep-14 | 2011-12 |
Total work in progress | 41,725 | 54,325 | 10,712 | 25,495 | 25,336 | 36,048 | - | - | - |
Projects Completed
Project |
Original project value $'000 |
Revised project value $'000 |
Prior year exp. $'000 |
Actual finance 2013-2014 $'000 |
Actual exp. 2013-2014 $'000 |
Total exp. to date $'000 | Estimated completion date | Actual completion date | Project approval year |
---|---|---|---|---|---|---|---|---|---|
Coombs Primary School design (finalisation of design) | 550 | 550 | 0 | 532 | 551 | 551 | Jun-14 | Jun-14 | 2013-14 |
Rectification and upgrade of Taylor Primary School | 12,930 | 13,731 | 6,256 | 8,336 | 7,475 | 13,731 | Dec-13 | Dec-13 | 2012-13 |
Installation of artificial grass surfaces – Stage 1 | 2,300 | 2,570 | 2,426 | 154 | 144 | 2,570 | Apr-13 | Apr-13 | 2011-12 |
Canberra College Cares (CCCares) program (design) | 1,400 | 1,400 | 562 | 839 | 839 | 1,401 | Jun-13 | Oct-13 | 2011-12 |
School toilet upgrade program - Stage 1 | 2,000 | 2,000 | 1,960 | 41 | 41 | 2,001 | Jun-13 | Oct-13 | 2011-12 |
School roof replacement program - Stage 1 | 2,800 | 4,029 | 2,780 | 1,249 | 1,249 | 4,029 | Sep-13 | Oct-13 | 2011-12 |
Coombs Primary School (design) | 1,950 | 1,950 | 1,309 | 641 | 641 | 1,950 | Jun-14 | Jun-14 | 2010-11 |
Harrison School (secondary school site) | 43,500 | 47,370 | 46,441 | 929 | 929 | 47,370 | Dec-11 | Dec-11 | 2009-10 |
Namadgi School | 50,000 | 55,550 | 55,474 | 152 | 76 | 55,550 | Apr-11 | Apr-11 | 2007-08 |
2012-13 childcare capital upgrades | 390 | 390 | 95 | 327 | 295 | 390 | Jun-13 | Dec-13 | 2012-13 |
Franklin Early Childhood School | 42,700 | 25,641 | 24,473 | -36 | 605 | 25,078 | Dec-13 | Jan-14 | 2011-12 |
Neville Bonner Primary School | 60,270 | 43,270 | 36,092 | 5,019 | 4,915 | 41,007 | Dec-13 | Jan-14 | 2011-12 |
Gungahlin College | 60,700 | 74,407 | 73,991 | 119 | 152 | 74,143 | Mar-11 | Mar-11 | 2007-08 |
Total projects completed | 281,490 | 272,858 | 251,859 | 18,302 | 17,912 | 269,771 | - | - | - |
Total Capital Works Program 2013-14
Project |
Original project value $'000 |
Revised project value $'000 |
Prior year exp. $'000 |
Actual finance 2013-2014 $'000 |
Actual exp. 2013-2014 $'000 |
Total exp. to date $'000 | Estimated completion date | Actual completion date | Project approval year |
---|---|---|---|---|---|---|---|---|---|
Total Capital Works Program 2013-14 | 360,315 | 411,275 | 262,571 | 63,940 | 64,258 | 326,829 | - | - | - |
Source: Education and Training Directorate
Table F3.2: End of year reconciliation schedule 2013-14
Reconciliation of total current year financing | $'000 |
---|---|
Total current year capital works financing | 58,095 |
Add: Financing of other capital initiatives | 9,314 |
Capital injection from Govt. per cash flow statement | 67,409 |
Reconciliation of total current year actual expenditure - against financing | $'000 |
---|---|
Total current year capital works expenditure | 59,095 |
Total current year capital initiatives expenditure | 17,888 |
Less: Net impact of accruals between financial years | -2,705 |
Less: Capital purchases funded outside of capital injections | -6,868 |
Capital injection from Govt. per cash flow statement | 67,409 |
Reconciliation of total current year actual expenditure | $'000 |
---|---|
Total current year capital works expenditure | 59,095 |
Add: Capital initiatives | 17,888 |
Add: Other asset purchases outside of capital works program | 1,537 |
Less: Net impact of accruals between financial years | -2,705 |
Purchase of property, plant and equipment as per cash flow statement | 75,814 |
Source: Education and Training Directorate