Follow us on:

Overview

In 2016-17, the Directorate delivered a capital works program, totalling $19.5 million, following on from the $41 million program in 2015-16 and $55.8 million program delivered in 2014-15.

Significant achievements for the year included the commencement of modernisation works at the Belconnen High School and the start of construction of the Caroline Chisholm School Centre for Innovation and Learning. Investment in Gungahlin School Infrastructure included the completion of expansion projects at Neville Bonner Primary School and Harrison School and additional capacity at Palmerston Preschool.

New Schools

North Gungahlin Primary School

Design and procurement activities progressed for the new school during the reporting period with the appointment of the preferred contractor to complete detailed design development.

The school is to be delivered under a Design Construct Maintain (DCM) construction methodology with construction commencing in late 2017 and completed for the start of the 2019 school year.

Caroline Chisholm School Centre for Innovation and Learning

The Centre for Innovation and Learning will deliver Science, Technology, Engineering and Mathematics (STEM) programs to students attending Caroline Chisholm School and in the Tuggeranong Network.

It includes multi-purpose learning spaces and state-of-art equipment and facilities to support students and provide professional development to teachers across the ACT public education system.

Construction commenced during the reporting period and is to be completed and operational for the commencement of the 2018 school year.

Modernising Belconnen High School

The next stage of the project commenced during the reporting period with the appointment of the preferred builder to complete design finalisation. Construction activities commenced with roof replacement works and site establishment.

The project includes major refurbishments to the student learning and teaching spaces, a new administration area and main entry, the demolition of an end of life building and additional outdoor works.

Investment in Gungahlin School Infrastructure

Expansion works were progressed at a number of schools in the North Gungahlin region to accommodate increased enrolment demand in the area.

Four new learning spaces and two preschool rooms were provided at Neville Bonner Primary School together with the expansion of Palmerston Preschool for the start of the 2017 school year. Harrison School was provided with eight new learning spaces in a new building during semester 1 of 2017 and a preferred contractor was identified to complete detailed design for the Amaroo School expansion works during 2017.

Capital Upgrades Program

School Upgrades

Works completed in the 2016-17 year included:

Building Compliance Upgrades

Building compliance upgrades and modifications completed during the report period included:

Air Conditioning in Schools

In 2015, a program commenced to ensure all ACT public schools had air conditioning or evaporative cooling in both library and administration areas. This program is largely complete, with some works to be finalised at Amaroo School by October 2017.

The cost of the program was $750,000 across the 2015-16 and 2016-17 years.

Library upgrades occurred at the following schools:

Administration area upgrades occurred at the following schools:

Ainslie Primary School chose to install air conditioning in two transportables under this program rather than in the administration area.

Environmental Sustainability

As capital works are undertaken at public schools, including new facilities, building upgrades and refurbishments, opportunities are taken to improve the energy efficiency, increase use of sustainable transport and decrease the water consumption of these spaces. Specific capital works directly targeting sustainability are also undertaken directly by schools. The key funding source for these projects is the feed-in-tariff income associated with the solar panels at schools.

A total of $0.80 million was allocated from the schools capital upgrades program during the reporting period to support the Directorate’s strategic priorities for environmental sustainability improvements. Refer to Section B9 for an overview of the projects and programs implemented during the 2016-17 reporting period.

Table C3.1: Capital Works Management 2016-17
ProjectOriginal Project Value
($’000)
Revised Project Value
($’000)
Prior Year Expenditure
($’000)
Actual Expenditure 2016-17
($’000)
Total Expenditure To Date
($’000)
Estimated CompletionActual Completion
New Capital Works
Better Schools –Investment in Gungahlin School Infrastructure16,60016,60004,3444,344Feb-18 
Capital Upgrades
School Learning Area Improvements6,5604,94104,6914,691Dec-17 
School Administration and Support Area Improvements1,4801,65901,2961,296Dec-17 
School Upgrades4,2255,33903,1853,185Dec-17 
School Security & Safety Improvements1,5051,49701,0871,087Dec-17 
Environmentally Sustainable Design Initiatives8007580334334Dec-17 
Total Capital Upgrades14,57014,194010,59310,593  
Total New Works31,17030,794014,93714,937  
Work in Progress
Schools for the Future – Caroline Chisholm School – Centre for Innovation and Learning5,8965,6962397741,013Feb-18 
Schools for the Future – Modernising Belconnen High17,62717,6271,1281,2892,417Feb-19 
Schools for the Future – North Gungahlin and Molonglo28,60928,6094848541,338Feb-19 
Hazardous Material Removal Program – Stage 33,0003,0002,0154932,508Jun-18 
Total Work In Progress55,13254,9323,8663,4107,276  
Projects – Physically But Not Financially Completed
Carbon Neutral Schools – Stage 13,5003,5003,2872043,491 Jun-17
Coombs P-6 School Construction Funding47,25035,75234,72841435,142 Jan-16
Belconnen Trade Skill Centres8,1208,1207,6065118,117 Jun-17
Total Projects Physically but not Financially Completed58,87047,37245,6211,12946,750  
Projects – Physically And Financially Completed
Sustainable Learning Trade Training Centres – Tuggeranong10,2078,3018,248538,301 Dec-14
Gungahlin College60,70076,70776,6931476,707 Mar-11
Total Projects Physically and Financially Completed70,90785,00884,9416785,008  
Total Capital Works Program 2016-17216,079218,106134,42819,543153,971 
Table C3.2: End of Financial Year Reconciliation Schedule 2016-17
Reconciliation of total current year financing 2016-17 $’000
Total current year capital works financing 18,396
Add: Other capital initiatives financing 7,574
Capital Injection from Government per Cash flow statement 25,970
Reconciliation of Total Current Year Actual Expenditure to Capital Injection
Total current year capital works expenditure 18,817
Total current year capital initiatives expenditure 8,285
Add: Net Impact of accruals between financial years -798
Less: Net Impact of Capital Expenditure Funded Outside of Capital Injections -334
Capital Injection from Government per Cash flow statement 25,970
Reconciliation of Total Current Year Actual Expenditure to Purchases of PPE
Total current year capital works expenditure 18,817
Total current year capital initiatives expenditure 8,285
Add: Net Impact of accruals between financial years -798
Add: Other asset purchases outside of capital works program and capital initiatives 2,664
Purchase of Property, Plant and Equipment as per Cash Flow Statement 28,968

For further information contact:
Director
Infrastructure and Capital Works
(02) 6205 1289

Back to Top